Action Prepare Release Test for De Danske Aviser

Assigned
PKO+JRG

Prev assigned

Tasks adressed
["Collection"]

Time estimated
4 md (pairwork)

Time used
3 md

Priority
2

Status
In progress

Iteration
17

Notes

Prepare release test (describing what should be checked, and what the success criteria are).

Structure of the release test may be inspired by release tests for the MiniDOMS for Aarbog - iterations 5,...,7. For example the [:Iteration7ReleaseTest:release test of iteration 7].

BR

---

BR

The definition of the steps in the release test is located [:ActionDDAReleaseTest:here].

In defining the release test, we still need to take care of the following.

BR

Checklist For Working On An Action

The Life Cycle of an Action:

Please make sure that you address the below issues, when working on an action: