Action Decide on example Collections

Assigned
EK+JRG

Prev assigned

Tasks adressed
None

Time estimated
not done

Time used
2md

Priority
?

Status
Finished

Iteration
10

Notes
Decide which collections should be used as basis for the examples given to Mjølner

Decided were reel tapes and radio news broadcast manuscripts, with Dansk Lydhistorie as candidate but complex due to HTML

Checklist For Working On An Action

Please make sure that you address the below issues, when working on an action:

  • Update the state of the action to "In Progress" when you start working on it.
  • Check if the tasks addressed by this action have their status set to "In Progress". If that is not the case, then change the state of them.
  • Keep track of how much time that has been spent working on the action. If it addresses more than one task, then make a note on the action page about how much of the elapsed time that has been spent on the individual tasks. Hint: Continually updating the "Time used" field will make it easier for you.

  • Update the "Progress History" and documentation pages of each task addressed by this action when appropriate. This depends on the situation, but in general, the task pages should hold all important related information about the work done, experiences gathered, identified requirements and so on.