Agendas 2007-11-19

0. Agenda walkthrough

1. Iteration 5 status

For each action:

Priority

Action Description

Estimated time

Tasks adressed

Responsible

Status

1

[:ActionDesignAndSalvageIngestModule:Design ingest module, migrate pre-analysis project ingest code]

12 md

["TaskA.4.1"]

TE (6 md), TSH (6 md)

Not started

1

[:ActionSalvageDataModel:Salvage data model from pre-analysis project, document, identify unresolved issues]

6 1/4 md

["TaskA.2.2"], ["TaskA.2.3"]

BAM (2 1/4), MKE (4)

In progress

3

[:ActionGentofte:Identify "Gentofte" objects, design datamode]

5½ md

["TaskA.2.2"] Collection

BAM (2), MKE(3½)

In progress

1

[:ActionStudyGroup:Study group with Asger and Jeppe: setup Idea/SVN, go through WBS, go through guidelines, identify relevant study material]

10½ md

["TaskF"] ["TaskG"]

TSH (½), KFC(1), JRG(4½), ABR(4½)

Not started

5

[:ActionRiskAndStakeholderResults:Present results of risk and stakeholder analysis and communication plan, plan actions suggested by these including communication with external partners]

4½ md

["TaskG.2"] ["TaskG.3"]

KFC(2), TSH(1½)

Not started

2

[:ActionReleasetest5:Prepare releasetest. Goal: Running the migrated ingest code on test objects in test setup. Use Fedora tools to see they are ingested properly]

5 md.

Release test

KFC(3½), TE(1½)

Not started

3. AOB