On 16-12-2008 the DOMS-team had a planning day where we broke down the DOMS system in parts. For each part we estimated percentages showing how far we are in implementing the part fully, and percentages showing how far we need to get in order to satisfy the political goal of a DOMS housing "De Danske Aviser" (that DOMS codenamed DOMS-Beta). == How far are we, and how far do we need to get ==

On 16-12-2008 the DOMS-team had a planning day where we broke down the DOMS system in parts. For each part we estimated percentages showing how far we are in implementing the part fully, and percentages showing how far we need to get in order to satisfy the political goal of a DOMS housing "De Danske Aviser" (that DOMS is codenamed DOMS-Beta).
Line 25: Line 27:

== How much time / manpower do we need to get it done ==
Line 27: Line 31:
Below follows The following were our estimates of how much intensive development time we need for meeting the required Avis-goal percentages.
The estimates were guessed for the two people (JRG and PKO) who have been assigned time in this low-priority DOMS-period.

'''Connection to real Summa'''
 * Simple harvester
   * Wrapping (2 md JRG)
   * Summa-input discussion (1 md JRG)
   * Code (4-5 md JRG)
 * index.xslt - general (3 md JRG)
 * html.xslt -> Avis? (4 md JRG + 4 md Niels/Gitte/Dorete)

'''Add file'''
 * Bitstorage part (5 - 8 md JRG)
 * GUI object manipulation (1 - 2 md JRG)
 * Object manipulation (2 - 3 md JRG)
 * File characterizer (1 - 2 md JRG)

'''Bit storage''' (1 md JRG)

'''Agreements with maintenance'''
 * Machines for installations and bitstorage (4 md JRG)
 * Install scripts and installation guide (8 md JRG)

'''Ingester for "De Danske Aviser"'''
 * FoxML ingest (1 md PKO)
 * Bulk file attach (10 md PKO + 10 md JRG)
 * Bulk publish -> Validator (4 - 6 md JRG)

'''Content "De Danske Aviser"'''
 * 3-4 content models (4 md PKO + 4 md JRG)
 * Templates (1 md JRG)
 * Schemas + learning (2 md PKO + 2 md ABR + 2 md EK)
 * Converting-batch-script/tool (20 - 40 md PKO + 7 md JRG)
 * Modelling (data model) (2 md PKO + 2 md JRG + 2 md EK)
 * (Pre)-Ingest of the product (including test + release test) (10 - 20 md PKO + 6 md JRG)



== With our given manpower, when can we be done ==

How far are we, and how far do we need to get

On 16-12-2008 the DOMS-team had a planning day where we broke down the DOMS system in parts. For each part we estimated percentages showing how far we are in implementing the part fully, and percentages showing how far we need to get in order to satisfy the political goal of a DOMS housing "De Danske Aviser" (that DOMS is codenamed DOMS-Beta).

Percentages are estimates

System part or chore

Status 16-12-2008

Needed for DOMS-Beta

Needed for final DOMS

DOMS-GUI

80%

80%

100%

DOMS-GUI-Summa

40%

not needed

100%

DOMS-GUI-Export

10%

not needed

100%

DOMS-GUI-Import Quadriga (streams)

10%

not needed

100%

DOMS-GUI-Import Horizon (poster)

10%

not needed

100%

Object creation

87%

not needed

100%

PID generator

65%

65%

100%

Fedora

80%

80%

100%

Validator

30%

30%

100%

License

0%

not needed

100%

LDAP

0%

not needed

100%

Connection to real Summa

30%

60%

100%

Add file

17%

60%

100%

Bit storage

80%

82%

100%

Agreements with maintenance

25%

100%

100%

Ingester for "De Danske Aviser"

30%

100%

100%

Content "De Danske Aviser"

0%

100%

100%

The bold-faced percentages relate to what needs to be done in order to meet the political goal of "De Danske Aviser".

How much time / manpower do we need to get it done

On 17-12-2008 the DOMS-team had a planning day where we gave first early estimates to the efforts needed for meeting the Avis-goal.

The following were our estimates of how much intensive development time we need for meeting the required Avis-goal percentages. The estimates were guessed for the two people (JRG and PKO) who have been assigned time in this low-priority DOMS-period.

Connection to real Summa

  • Simple harvester
    • Wrapping (2 md JRG)
    • Summa-input discussion (1 md JRG)
    • Code (4-5 md JRG)
  • index.xslt - general (3 md JRG)
  • html.xslt -> Avis? (4 md JRG + 4 md Niels/Gitte/Dorete)

Add file

  • Bitstorage part (5 - 8 md JRG)
  • GUI object manipulation (1 - 2 md JRG)
  • Object manipulation (2 - 3 md JRG)
  • File characterizer (1 - 2 md JRG)

Bit storage (1 md JRG)

Agreements with maintenance

  • Machines for installations and bitstorage (4 md JRG)
  • Install scripts and installation guide (8 md JRG)

Ingester for "De Danske Aviser"

  • FoxML ingest (1 md PKO)
  • Bulk file attach (10 md PKO + 10 md JRG)
  • Bulk publish -> Validator (4 - 6 md JRG)

Content "De Danske Aviser"

  • 3-4 content models (4 md PKO + 4 md JRG)
  • Templates (1 md JRG)
  • Schemas + learning (2 md PKO + 2 md ABR + 2 md EK)
  • Converting-batch-script/tool (20 - 40 md PKO + 7 md JRG)
  • Modelling (data model) (2 md PKO + 2 md JRG + 2 md EK)
  • (Pre)-Ingest of the product (including test + release test) (10 - 20 md PKO + 6 md JRG)

With our given manpower, when can we be done