TODO

Iteration Actions

The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the [:WBS:Work Breakdown Structure] (WBS).

Each action is associated with a priority and a status. The priority indicates the importance of the completion of the action, where the highest priority is indicated with 1, and the status indicates the current state of the action. The state may be one of the following: "Not Started", "In Progress" and "Completed".

Priority

Action Description

Estimated time

Tasks adressed

Responsible

Status

1

Communicating results of TDR requirement analysis

2md

["TaskC.1"]

kfc, bam

Done

2

Add preingesting to test deployment system

2md

["TaskF.5"]

te, mke

In progress

1

Review of documentation

1md

["TaskF.5"]

mke, owners of documentation

In progress

1

Review of guidelines

3md

["TaskF.1"], ["TaskF.2"], ["TaskF.4"]

mke, owner of guidelines

In progress

1

[:AddDescriptionsToWBSTasks:Revise the descriptions of the WBS tasks]

2md

["TaskG.4"] ["WBS"]

kfc, tsh

In progress

1

Review and estimate final WBS tasks

3md

["TaskG.4"] ["WBS"]

kfc, alle

Not Started

1

[:IdentifyStakeholders:Identify the current stakeholders of the project.]

3md

["TaskG.2"]

tsh, kfc

Not Started

1

[:IdentifyRisks:Identify the current risks of the project.]

2md

["TaskG.3"]

tsh, kfc

Not Started

3

[:ClarifyBitStorage:Clarify any issues with IT regarding bit storage.]

2md

["TaskA.3"]

te, kfc

Not Started

1

Releasetest definition

1md

-

mke, kfc

Not Started

1

Releasetest

1md

-

Not Started