Reaching milestone 3

Begun
Unknown
Finished
2008-08-12
Due
Unknown
Status
Finished
Title
Get Mjølner Started

Purpose

The purpose of the iteration is to enable Mjølner to start working with DOMS. As such, we focus on providing an interface to the repository, as well as ways to describe datamodels.

Iteration Actions

The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the [:WBS:Work Breakdown Structure] (WBS).

Each action is associated with a priority, estimated time, tasks addressed, responsible developers and a status. The priority indicates the importance of the completion of the action, where the highest priority is indicated with 1, and the status indicates the current state of the action. The state may be one of the following: "Not Started", "In Progress" and "Finished".

When an iteration ends please walk through the actions and follow these steps on the "iteration end meeting":

PageDicts(Action, Priority, Time used, Time estimated, Assigned, Status, Tasks adressed,Notes,Iteration ~= 10)