Iterations
The below list contains all planned and completed iterations for this project.
Number |
Iteration Description |
Due Date |
1 |
[:Iteration1:Planning and infrastructure] |
19/07/07 |
2 |
[:Iteration2:Development Environment, Risk and Stakeholder Clarifications] |
|
3 |
[:Iteration3:Reaching milestone 1] |
|
4 |
[:Iteration4:Reviews and projects analysis] |
|
5 |
[:Iteration5:Starting DOMS framework on test collection] |
2007-11-22 |
6 |
[:Iteration6:Testcollection ready] |
|
7 |
[:Iteration7:Summa integration and bit storage] |
2008-01-31 |