Size: 2242
Comment: Created by the PackagePages action.
|
Size: 2734
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 10: | Line 10: |
||<10% style="text-align: center;">3 ||<style="text-align: left;">[:Milestone3:Get mjølner started] ||<15% style="text-align: center;">Late June 2008 || | ||<10% style="text-align: center;">3 ||<style="text-align: left;">[:Milestone3:Get Mjølner started] ||<15% style="text-align: center;">September 12, 2008 || ||<10% style="text-align: center;">4 ||<style="text-align: left;">[:Milestone4:Complete datamodel and DOMS interface] ||<15% style="text-align: center;">October 17, 2008 || ||<10% style="text-align: center;">5 ||<style="text-align: left;">[:Milestone5:Data Model Validation] ||<15% style="text-align: center;">November 7, 2008 || ||<10% style="text-align: center;">6 ||<style="text-align: left;">[:Milestone6:Production System] ||<15% style="text-align: center;">December 1, 2008 || |
Milestones
The below table contains all planned and completed milestones for this project.
Number |
Title |
Due date |
1 |
[:Milestone1:Planning, infrastructure and project setup] |
2007-10-16 |
2 |
[:Milestone2:Early ingest and trivial search - Temporary production system] |
Early 2008 |
3 |
[:Milestone3:Get Mjølner started] |
September 12, 2008 |
4 |
[:Milestone4:Complete datamodel and DOMS interface] |
October 17, 2008 |
5 |
[:Milestone5:Data Model Validation] |
November 7, 2008 |
6 |
[:Milestone6:Production System] |
December 1, 2008 |
More milestones to be defined.
Milestone revision notes:' See OldMilestones Other "tanks"....