Milestones
The below table contains all planned and completed milestones for this project.
Number |
Title |
Due date |
1 |
[:Milestone1:Planning, infrastructure and project setup] |
2007-10-16 |
2 |
[:Milestone2:Early ingest and trivial search - Temporary production system] |
Early 2008 |
3 |
[:Milestone3:Get MjĂžlner started] |
September 12, 2008 |
4 |
[:Milestone4:Complete datamodel and DOMS interface] |
October 17, 2008 |
5 |
[:Milestone5:Data Model Validation] |
November 7, 2008 |
6 |
[:Milestone6:Production System] |
December 1, 2008 |
7 |
[:Milestone7:To be defined] |
?? |
More milestones to be defined. Outstanding issues are at least all access, and rights management!
Milestone revision notes:'