2008-08-12 End of Summer Iterations Meeting
Attendants: KFC, ABR, TSH, EK, BAM
[:Agendas/2008-08-12:Agenda]
0. Praticalities
KFC created a new [:Manning:Manning wiki page] to make planning easier.
1. Forcefully ending iteration 9 and 10
Note: Actions cannot be pushed. Instead finish the action, when the iteration finishes, and create a new action in the new iteration.
- [:Iteration09:Iteration 9]
- Action Action Checklist
We discovered that the wiki transfer was not complete. The pages that were transferred early on (templates and structure), were not updated when the full wiki was transferred. TSH will make a list of the affected pages. New action.
Forced finish. Still missing something -> new action
We also need a new action to update tasks affected in iterations 9+10
- Action Finish Mini DOMS
Not started. Move action to later iteration.
- Action Milestone Plan
- Forced finish. Continue as part of status meetings.
- Action Mjoelner Timeframe
- Action Update Task List
- Action Wiki Magic
- Action Action Checklist
2. Iteration 11