Milestone 6 Metadata manager
Success Criteria
Tasks To Complete
The below table contains a list of all the tasks from the [:WBS:Work Breakdown Structure] (WBS) that must be completed at this milestone. Each of the tasks has a priority indicating the importance of completion, where 1 is the higest priority.
Priority |
Task Title |
1 |
["TaskA.2.3"] (partial, 33%) |
1 |
["TaskE.1"] (partial, 50%) |
1 |
["TaskE.3"] (partial, 50%) |
1 |
["TaskD.3.2"] (partial, 50%) |
1 |
["TaskD.3.3"] (partial, 50%) |