Risk Description
Project takes longer than estimated.
Our experience is that we are not perfect at estimating how long it will take to complete a certain task. Thus there is risk that the project will be delayed by poor estimation
However, unless the estimates start to slide wildly, the impact isn't great: it will simply take longer to implement the DOMS.
When to react?
When a general tendency towards not meeting deadlines shows up
Reaction
We should re-estimate our tasks and have the new estimates approved by the steering committee.
Responsible Persons
The below persons are responsible for continuously monitoring and acting on this risk: