C.1. Identify TDR Requirements

State: In progress

Time used: 1 3/4 md. Note: Time spent before iteration 3 not registered.; iteration 11: 1 md

Description

Documentation

Parent task

Progress history

Iteration Time used Status Notes
ActionDataModelTDRRequirements 11 1.5md Finished

2007-09-24

The analysis document has been updated with all requirements, and tasks have been identified that should address these requirements. We have also had to introduce some new tasks.

Please see the analysis document for more information.

2008-08-28

In connection with ActionDataModelTDRRequirements, we discovered that all references to 'RLG/NARA audit checklist' in the analysis document was to an 'old' version (and the link to this version was dead). The analysis document has now been updated with links to both old and new version. We should take time to go through the revised TRAC: Criteria and Checklist. We could also take a look at the Platter checklist.