G.4. Work Breakdown
State: In progress
Time used: 6 md. Note: Time used before iteration 3 not measured.
Description
The Work Breakdown Structure ([:WBS:]) page must be reviewed and revised regularly, say at the end of each iteration, to ensure that any emerged subtasks are added, time consumption and time estimates are updated.
Any emerged sub tasks must be added to the [:WBS:] using the TaskTemplate.
This task will be active during the whole project.
Parent task
- ["TaskG"]
Progress history
PageDicts(Action,Iteration, Time used,Status,Notes,Tasks adressed ~= TaskG.4)
2007-09-24
All WBS tasks have had descriptions of the task added. Some revision has been done in the progress.