Line 18: Line 18:
 Time estimated:: 8md  Time estimated:: 10md
Line 30: Line 30:

The above assumes continuous documentation during the Evolution phase, where the design is also altered in accordance with users requirements.

Determine the needs of the users

Title
Determine the needs of the users

State
Not started, Confidence A

Time used
0

Time estimated
10md

Description

For the process of revealing the needs of the users, we will need one person available from the user-base and one from the design team.

The person from the design team will, on the first two days, follow a person from the user-base in order to gain sufficient knowledge of the users challenges to make a first draft for user approval/alteration.

The remaining man-days will be spent in a precess of Evaluation<-->Evolution where the contact between the design team and the users will be limited to 2-3hour sessions.

The above assumes continuous documentation during the Evolution phase, where the design is also altered in accordance with users requirements.

Sub tasks

Title State Time used Time estimated

Documentation

Progress history

Iteration Time used Status Notes Tasks adressed