Differences between revisions 5 and 6
Revision 5 as of 2010-06-07 12:49:51
Size: 2929
Editor: eab
Comment:
Revision 6 as of 2010-06-09 07:16:49
Size: 2406
Editor: eab
Comment:
Deletions are marked like this. Additions are marked like this.
Line 25: Line 25:
For the process of revealing the needs of the users, we will need one person available from the user-base and one from the design team.
Line 27: Line 26:
The person from the design team will, on the first two days, follow a person from the user-base in order to gain sufficient knowledge of the users challenges to make a first draft for user approval/alteration.
Line 29: Line 27:
The remaining man-days will be spent in a precess of '''Evaluation<-->Evolution''' where the contact between the design team and the users will be limited to 2-3hour sessions.

Determine the needs of the users

Title
Determine the needs of the users

State
Not started, Confidence A

Time used
0

Time estimated
10md

Description

The above assumes continuous documentation during the Evolution phase, where the design is also altered in accordance with users requirements.

Sub tasks

Title State Time used Time estimated

Documentation

Progress history

Iteration Time used Status Notes Tasks adressed

Tasks/34/1/1 (last edited 2010-06-09 07:21:15 by eab)