Action System Setup Agreement
As the miniDOMS is to be handed over to Maintenance, we need to have responsibilities specified. This include:
- (DONE) Who will perform the ingest of objects to miniDOMS
- (DONE) The final bitstorage system must be established, and agreed to by both parties
- (DONE) The tomcat server must be installed, and maintenance of it must be agreed. The tomcat server must be configured to use Fedora.
Total: Probably 1-2 meetings. 2 md, so that 2 persons can use 1 entire day for meetings. This should be enough.
- (3 md) A general procedure for bug reports and failure handling between the DOMS team and Maintenance must be agreed upon. Helpdesk must be notified.
In addition:
- We need to make an agreement with Maintenance about when the work above will be completed.
Current status
DONE, if no complains arise.
13/3-08 We have reached a new agreement with the Maintenance department, described in Production Agreement
Time used: (ABRs estimates, change as you like)
- ABR: 6h
- JRG: 2h
- KFC: 5h
Old Ressources
We have met with Drift, to determine what they can deliver, and when. The results of this can be seen in: