Agenda 2007-11-05
0. Agenda walkthrough
1. Presentation and welcome of new members
2. Iteration process
A quick breakdown of the life cycle of an iteration:
- Startup meeting (1 day) 
- Select actions
 - Assign actions
 
 - Describe actions (1-2 days) 
- Assigned persons describe design and estimate needed resources 
- For estimation, remember all the tasks below: design, unittests, reviews, followups
 
 - Design writers swap descriptions for review/comments
 
 - Assigned persons describe design and estimate needed resources 
 Assign persons to actions, set iteration end date (<½ day)
- Implement actions (5-10 days) 
- Write detailed (code) design
 - Write unit tests
 - Implement action
 - Review with someone not assigned to action
 - Review followup
 
 - Release test (1-2 days)
 - End of iteration meeting 
- Information exchange
 - Followup on estimation
 
 
3. Iteration 5 breakdown
Suggested actions:
- TE, TSH Design ingest module, migrate pre-analysis project ingest code
 - BAM, MKE Salvage data model from pre-analysis project, document, identify unresolved issues
 - BAM, TE Identify "Gentofte" objects, design datamodel
 - TSH, MKE, JRG, ABR Study group with Asger and Jeppe: setup Idea/SVN, go through WBS, go through guidelines, identify relevant study material
 - TSH, KFC Present results of risk and stakeholder analysis and communication plan, plan actions suggested by these including communication with external partners
 - KFC, TE Prepare releasetest. Goal: Running the migrated ingest code on test objects in test setup. Use Fedora tools to see they are ingested properly.
 
x. AOB
- Planning of weekly meetings