Agendas 2007-11-12
0. Agenda walkthrough
1. Iteration 5 status
For each action:
- Action status (not started, in progress, done), time spent
 - Do estimates seem to hold
 - Does deadline seem to hold
 - Any information that should be shared
 - Any planning we need to do
 
Priority  | 
  Action Description  | 
  Estimated time  | 
  Tasks adressed  | 
  Responsible  | 
  Status  | 
1  | 
  [:ActionDesignAndSalvageIngestModule:Design ingest module, migrate pre-analysis project ingest code]  | 
  12 md  | 
  ["TaskA.4.1"]  | 
  TE (6 md), TSH (6 md)  | 
  Not started  | 
1  | 
  [:ActionSalvageDataModel:Salvage data model from pre-analysis project, document, identify unresolved issues]  | 
  6 1/4 md  | 
  ["TaskA.2.2"], ["TaskA.2.3"]  | 
  BAM (2 1/4), MKE (4)  | 
  In progress  | 
3  | 
  [:ActionGentofte:Identify "Gentofte" objects, design datamode]  | 
  5½ md  | 
  ["TaskA.2.2"] Collection  | 
  BAM (2), MKE(3½)  | 
  In progress  | 
1  | 
  [:ActionStudyGroup:Study group with Asger and Jeppe: setup Idea/SVN, go through WBS, go through guidelines, identify relevant study material]  | 
  10½ md  | 
  ["TaskF"] ["TaskG"]  | 
  TSH (½), KFC(1), JRG(4½), ABR(4½)  | 
  Not started  | 
5  | 
  [:ActionRiskAndStakeholderResults:Present results of risk and stakeholder analysis and communication plan, plan actions suggested by these including communication with external partners]  | 
  4½ md  | 
  ["TaskG.2"] ["TaskG.3"]  | 
  KFC(2), TSH(1½)  | 
  Not started  | 
2  | 
  [:ActionReleasetest5:Prepare releasetest. Goal: Running the migrated ingest code on test objects in test setup. Use Fedora tools to see they are ingested properly]  | 
  5 md.  | 
  Release test  | 
  KFC(3½), TE(1½)  | 
  Not started  | 
3. AOB
- KFC Meeting with Media Department today 10.45
 - Use of project room