Agendas 2007-11-12

0. Agenda walkthrough

1. Iteration 5 status

For each action:

Priority

Action Description

Estimated time

Tasks adressed

Responsible

Status

1

Design ingest module, migrate pre-analysis project ingest code

12 md

TaskA.4.1

TE (6 md), TSH (6 md)

Not started

1

Salvage data model from pre-analysis project, document, identify unresolved issues

6 1/4 md

TaskA.2.2, TaskA.2.3

BAM (2 1/4), MKE (4)

In progress

3

Identify "Gentofte" objects, design datamode

5½ md

TaskA.2.2 Collection

BAM (2), MKE(3½)

In progress

1

Study group with Asger and Jeppe: setup Idea/SVN, go through WBS, go through guidelines, identify relevant study material

10½ md

TaskF TaskG

TSH (½), KFC(1), JRG(4½), ABR(4½)

Not started

5

Present results of risk and stakeholder analysis and communication plan, plan actions suggested by these including communication with external partners

4½ md

TaskG.2 TaskG.3

KFC(2), TSH(1½)

Not started

2

Prepare releasetest. Goal: Running the migrated ingest code on test objects in test setup. Use Fedora tools to see they are ingested properly

5 md.

Release test

KFC(3½), TE(1½)

Not started

3. AOB