Install-sequence for parts of the DOMS system, including its environment
The sequence in which each part should be installed, for integration of DOMS with Radio/TV.
Step 1
The following three can be installed in any order
Step 2
Install DOMS Ingester
depends on DOMS
Install Summa (backend)
depends on DOMS
Step 3
Install Wowza with plugins
depends on DOMS and Broadcast Extraction Service (BES)
Install Broadcast Extraction Service (BES)
depends on Wowza with plugins and DOMS
Step 4
Install Web frontend (Radio/TV DOMS Portal)
depends on Broadcast Extraction Service (BES), Wowza with plugins, Summa (backend), IP Role-mapper and DOMS
Locations of different parts (in integration test)
DOMS
- Auth checker: port 7980, otherwise "as usual"
- Ticket issuer: port 7980, otherwise "as usual"
IP Role-mapper: port 7950, otherwise "as usual"
Wowza with plugins
- Streaming URL:
- rtmp://iapetus:1937/doms
- rtmp://iapetus:1937/domslive
- Media files location:
- iapetus:/home/doms/streamingContent
- iapetus:/home/doms/streamingContentLive
- Streaming URL:
Status of the different install units (for stage)
Install unit |
Status |
Next action |
DOMS |
(2011-01-27) Stage candidate 5 submitted |
ready for stage test.. |
DOMS Ingester |
(2011-01-14) Stage candidate 1 submitted, accepted |
ready for stage test.. |
DigiTV |
(2011-01-20) Stage candidate 10 submitted, accepted |
ready for stage test.. |
IP Role-mapper |
(2010-??-??) Stage candidate 1 submitted, accepted |
ready for stage test.. |
Summa (backend) |
(2011-01-24) Stage candidate 3 submitted, accepted |
ready for stage test.. |
Wowza with plugins |
(2011-01-27) Stage candidate 3 submitted, accepted |
ready for stage test.. |
Broadcast Extraction Service (BES) |
(2011-01-06) Stage candidate 1 submitted, accepted |
ready for stage test.. |
Web frontend (Radio/TV DOMS Portal) |
(2011-01-17) Stage candidate 1 submitted, accepted |
ready for stage test.. |
Once in stage, only maintenance may run scripts - and need to be ping'ed for running anything needed for testing. DOMS + DigiTV + Summa people will get read-only access for inspecting the results of stage tests. Tests of the system as a whole is described here: Stage-Test of DOMS RadioTV System.
NOTICE: As we go PROD, we will need atleast one day (before communicating prod to doms control group) in order to be able to test that our system can indeed be reached by the two machines on "fagsalen", and indeed cannot be reached by people outside.