The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the [:WBS:Work Breakdown Structure] (WBS). | The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the [[WBS|Work Breakdown Structure]] (WBS). |
Line 24: | Line 24: |
|| ||<(>[:ActionWritePreingestForTestCollection:Write the pre-ingest for test collection. ] || || ["TaskA.4.2"], ["TaskA.4.3"]|| JRG+ABR || In progress || || ||<(>[:ActionFollowupOnOutstandingDatamodelIssues:Followup on outstanding Datamodel Issues. ] || || ["TaskA.2.2"], ["TaskA.2.3"] || KFC || Not Started || || ||<(>[:ActionOpenSourcing:Early open-sourcing of DOMS. ] || || None(!)|| || Postponed to later iteration || || ||<(>[:ActionReleaseTest6:Release Test ] || || Release test|| || Postponed to later iteration || || ||<(>[:ActionDescribeIterationWorkFlow:Describe the iteration workflow and make a check-list. ] || || || || Postponed to later iteration || |
|| ||<(>[[ActionWritePreingestForTestCollection|Write the pre-ingest for test collection. ]] || || [[TaskA.4.2]], [[TaskA.4.3]]|| JRG+ABR || In progress || || ||<(>[[ActionFollowupOnOutstandingDatamodelIssues|Followup on outstanding Datamodel Issues. ]] || || [[TaskA.2.2]], [[TaskA.2.3]] || KFC || Not Started || || ||<(>[[ActionOpenSourcing|Early open-sourcing of DOMS. ]] || || None(!)|| || Postponed to later iteration || || ||<(>[[ActionReleaseTest6|Release Test ]] || || Release test|| || Postponed to later iteration || || ||<(>[[ActionDescribeIterationWorkFlow|Describe the iteration workflow and make a check-list. ]] || || || || Postponed to later iteration || |
Testcollection ready
- Begun
- 2007-12-03
- Finished
- 2007-12-18
- Status
- Finished
- Due
- Title
- Testcollection ready
In this iteration we will finish the datamodel and write preingest of test collection, so we have a finished test collection for use in further work.
Iteration Actions
The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the Work Breakdown Structure (WBS).
Each action is associated with a priority, estimated time, tasks addressed, responsible developers and a status. The priority indicates the importance of the completion of the action, where the highest priority is indicated with 1, and the status indicates the current state of the action. The state may be one of the following: "Not Started", "In Progress" and "Completed".
Priority |
Action Description |
Estimated time |
Tasks adressed |
Responsible |
Status |
|
|
JRG+ABR |
In progress |
||
|
|
KFC |
Not Started |
||
|
|
None(!) |
|
Postponed to later iteration |
|
|
|
Release test |
|
Postponed to later iteration |
|
|
|
|
|
Postponed to later iteration |