Action Open Source DOMS
- Assigned
- KFC(2md), PKO(2md), JRG(1md)
- Prev assigned
- Tasks adressed
- Time estimated
- 5md
- Time used
- 2md(JRG), 5md(KFC)
- Priority
- 5
- Status
- In progress
- Iteration
- 21
- Notes
Things to take care of:
- Choose which parts of our current svn contents should go to open source. (DONE)
Agree on a proper directory structure for what should be open sourced. (DONE, see Directory Layout)
If needed, update our guidelines for Directory Layout (DONE) and Module Release Structure
- Build directory structure - for now only for: ECM, bitstorage integration (DONE), domsserver (DONE), and for domsclient
- Upload to source forge - for now only for: ECM, bitstorage integration (DONE), domsserver (DONE), and for domsclient
- Write headers in code
Checklist For Working On An Action
The Life Cycle of an Action:
Assign people for action definition: Done at start of iteration status meeting. Fill out Assigned
Define the action: Describe information about what is to be done and how. Fill out Tasks Addressed and Time Estimated.
Review the definition: Get another project group member to review the action definition, and update it.
Assign people for action implementation: Done by project manager, usually the same persons who wrote the definition. Fill out Assigned and Prev assigned if new persons are assigned.
Implement the action: See details below
Review the action: Get another project group member to review what is implemented (code and documentation), and update it.
Finish the action: Change the status to "Finished" and update the "time used" field on the action page.
Please make sure that you address the below issues, when working on an action:
- Update the state of the action to "In Progress" when you start working on it.
- Check if the tasks addressed by this action have their status set to "In Progress". If that is not the case, then change the state of them.
Keep track of how much time that has been spent working on the action. If it addresses more than one task, then make a note on the action page about how much of the elapsed time that has been spent on the individual tasks. Hint: Continually updating the "Time used" field will make it easier for you.
- Update the "Progress History" and documentation pages of each task addressed by this action when appropriate. This depends on the situation, but in general, the task pages should hold all important related information about the work done, experiences gathered, identified requirements and so on.