Reaching Milestone 1
- Begun
- Finished
- Status
- Finished
- Due
- Title
- Reaching Milestone 1
TODO
Iteration Actions
The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the Work Breakdown Structure (WBS).
Each action is associated with a priority and a status. The priority indicates the importance of the completion of the action, where the highest priority is indicated with 1, and the status indicates the current state of the action. The state may be one of the following: "Not Started", "In Progress" and "Completed".
Priority |
Action Description |
Estimated time |
Tasks adressed |
Responsible |
Status |
1 |
Communicating results of TDR requirement analysis |
2md |
kfc, bam |
Done |
|
2 |
Add preingesting to test deployment system |
2md |
te, mke |
In progress |
|
1 |
Review of documentation |
1md |
mke, owners of documentation |
In progress |
|
1 |
Review of guidelines |
3md |
mke, owner of guidelines |
In progress |
|
1 |
2md |
kfc, tsh |
In progress |
||
1 |
Review and estimate final WBS tasks |
3md |
kfc, alle |
Not Started |
|
1 |
3md |
tsh, kfc |
Not Started |
||
1 |
2md |
tsh, kfc |
Not Started |
||
3 |
2md |
te, kfc |
Not Started |
||
1 |
Releasetest definition |
1md |
- |
mke, kfc |
Not Started |
1 |
Releasetest |
1md |
- |
|
Not Started |