Iteration 13 - Solidifying the DOMS datamodel and interface

Begun
2008-09-22
Finished
2008-10-21
Due
2008-10-17
Status
Finito
Title
Solidifying the DOMS datamodel and interface

Iteration Actions

The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the Work Breakdown Structure (WBS).

Each action is associated with a priority, estimated time, tasks addressed, responsible developers and a status. The priority indicates the importance of the completion of the action, where the highest priority is indicated with 1, and the status indicates the current state of the action. The state may be one of the following: "Not Started", "In Progress" and "Finished".

When an iteration ends please walk through the actions and follow these steps on the "iteration end meeting":

Priority Time used Time estimated Assigned Status Tasks adressed Notes
ActionImportExportAPIs 2 ½md (KFC) 2md KFC+ABR In progress [[TaskE.1]]
ActionMetadataStandards 1 1.5h 5½md + Elsebeths time KFC+JRG+EK Not started [[TaskA.2]]
ActionSystemDocumentation 4 4md 5md JRG+ABR In progress [[TaskD.6]] Depends on "Action WSDL2 Java"
ActionUpdateDatamodelDocumentation 5 2md 5md ABR+JRG+KFC In progress [[TaskA.2]]
ActionViewDatastream 6 0md 2md ABR+KFC Described, lacks review [[TaskB.2]],[[TaskB.1]]
ActionWSDL2Java 3 2½md 3md BAM + JRG Finished [[TaskB.5]] wsdl2Java + 'provide documented wsdl' functionality postponed