Extra APIs, and validation

Begun
2008-10-27
Finished
2008-11-07
Due
2008-11-07
Status
Done
Title
Extra APIs, and validation

Iteration Actions

The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the Work Breakdown Structure (WBS).

Each action is associated with a priority, estimated time, tasks addressed, responsible developers and a status. The priority indicates the importance of the completion of the action, where the highest priority is indicated with 1, and the status indicates the current state of the action. The state may be one of the following: "Not Started", "In Progress" and "Finished".

When an iteration ends please walk through the actions and follow these steps on the "iteration end meeting":

Priority Time used Time estimated Assigned Status Tasks adressed Notes
ActionCreateObjectFromTemplateObject 1 3.5 md 2md TSH+JRG+KFC Finished [[TaskE.1]]
ActionFeedbackFromMjolner 1 0md 3 TSH+BAM In progress [[TaskE.1]]
ActionHowToDeleteObjects 1 0.5md 1md ABR+TSH+BAM Finished [[TaskA.5]]
ActionImportExportExamples 2 ~1md BAM + ... 5md KFC+BAM+TSH Finished [[TaskE.1]] Export punted
ActionRISearchWrapper 1 2.5md 2md ABR+JRG Finished [[TaskA.5]]
ActionValidator 2 0md not done KFC+ABR Description in progress [[TaskA.4]], [[TaskC.3]]