Final bits for Mjølner

Begun
2008-12-01
Finished
2008-12-15
Due
2008-12-15
Status
Closed
Title
Final bits for Mjølner

Iteration Actions

The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the Work Breakdown Structure (WBS).

Each action is associated with a priority, estimated time, tasks addressed, responsible developers and a status. The priority indicates the importance of the completion of the action, where the highest priority is indicated with 1, and the status indicates the current state of the action. The state may be one of the following: "Not Started", "In Progress" and "Finished".

When an iteration ends please walk through the actions and follow these steps on the "iteration end meeting":

Priority Time used Time estimated Assigned Status Tasks adressed Notes
ActionBitStorageFinalMaintenanceAgreements 3 0md not done BAM+ABR Not described [[TaskX/1]]
ActionBitStorageForReal 5 0md not done ABR+? Not described [[TaskX/1]]
ActionBitStorageWebservicePartTwo 2 ½md (BAM) 1-3md BAM, ABR, (TSH) Finished. [[TaskA.4]], [[TaskA.5]] Need fix todos action later
ActionExampleContentModelsAndTemplates 1 1md(BAM) + 1md(JRG) + ?(ABR) 3md BAM+JRG In progress [[TaskX/1]]
ActionExportWebserviceContinued 5 0md 1/4 md BAM+? Finished. [[TaskX/1]] only mock-up
ActionPWRemoveContinued 3 ½md 2md BAM+? Description not reviewed [[TaskX/1]] also localhost:8080
ActionSchemaUpdatesContinued 3 0md not done ABR+? Not described [[TaskX/1]]
ActionTrueSearchContinued 1 0md 12½md ABR+JRG In progress [[TaskB.1]], [[TaskB.2]]
ActionValidationFinishingContinued 6 0md not done ABR+? Not described [[TaskX/1]]