Milestone Planning, infrastructure and project setup
Success Criteria
- One-click installation of Fedora, database and DOMS-release-package in testenvironment, has been run by everyone in the project, and reviewed documentation for the process exists.
- Written conclusions on cooperation plan with IT about bit preservation
- Finished estimation of tasks for trusted repository
- Documentation guidelines as below finished and reviewed
- Development guidelines finished and reviewed
- Development environment testing code for compilation and unit tests at least daily
- WBS ready
- Risk analysis accepted by BJA
- Stakeholders identified, communication plan made and accepted by BJA
Tasks To Complete
The below table contains a list of all the tasks from the Work Breakdown Structure (WBS) that must be completed at this milestone. Each of the tasks has a priority indicating the importance of completion, where 1 is the higest priority.
Priority |
Task Title |
10 |
Meeting with IT to coordinate bitstorage - TaskA.3 (partial) |
3 |
Meeting with planets/DPE to identify requirements for digital repositories - TaskC.1 (partial), TaskC.2 (partial) |
6 |
Prepare final written guidelines for documentation - TaskD.1.1, TaskD.1.2, TaskD.1.4 |
4 |
Prepare final written developer guidelines TaskD.2.* |
2 |
Write partial system documentation TaskD.3.2 (partial) |
2 |
Prepare stop/start-scripts for DOMS TaskE.3.2 |
1 |
Prepare project environment TaskF* |
4 |
Stakeholder analysis including communication plan TaskG.2 |
4 |
Risk analysis TaskG.3 |
7 |
Remaining estimates - TaskG.1 |