Line 15: Line 15:
||1 || [:ActionDesignAndSalvageIngestModule:Design ingest module, migrate pre-analysis project ingest code] || 12 md || ["TaskA.4.1"] ||TE (6 md), TSH (6 md) || Not started ||
||1 || [:ActionSalvageDataModel:Salvage data model from pre-analysis project, document, identify unresolved issues] || 6 1/4 md || ["TaskA.2.2"], ["TaskA.2.3"] ||BAM (2 1/4), MKE (4) ||In progress ||
||3 || [:ActionGentofte:Identify "Gentofte" objects, design datamode] || 5½ md || ["TaskA.2.2"] Collection ||BAM (2), MKE(3½) || In progress||
||1 || [:ActionStudyGroup:Study group with Asger and Jeppe: setup Idea/SVN, go through WBS, go through guidelines, identify relevant study material] || 10½ md || ["TaskF"] ["TaskG"] || TSH (½), KFC(1), JRG(4½), ABR(4½) || Not started ||
||5 || [:ActionRiskAndStakeholderResults:Present results of risk and stakeholder analysis and communication plan, plan actions suggested by these including communication with external partners] ||4½ md || ["TaskG.2"] ["TaskG.3"] ||KFC(2), TSH(1½) || Not started ||
||2 || [:ActionReleasetest5:Prepare releasetest. Goal: Running the migrated ingest code on test objects in test setup. Use Fedora tools to see they are ingested properly] || 5 md. || Release test ||KFC(3½), TE(1½) || Not started ||
||1 || [[ActionDesignAndSalvageIngestModule|Design ingest module, migrate pre-analysis project ingest code]] || 12 md || [[TaskA.4.1]] ||TE (6 md), TSH (6 md) || Not started ||
||1 || [[ActionSalvageDataModel|Salvage data model from pre-analysis project, document, identify unresolved issues]] || 6 1/4 md || [[TaskA.2.2]], [[TaskA.2.3]] ||BAM (2 1/4), MKE (4) ||In progress ||
||3 || [[ActionGentofte|Identify "Gentofte" objects, design datamode]] || 5½ md || [[TaskA.2.2]] Collection ||BAM (2), MKE(3½) || In progress||
||1 || [[ActionStudyGroup|Study group with Asger and Jeppe: setup Idea/SVN, go through WBS, go through guidelines, identify relevant study material]] || 10½ md || [[TaskF]] [[TaskG]] || TSH (½), KFC(1), JRG(4½), ABR(4½) || Not started ||
||5 || [[ActionRiskAndStakeholderResults|Present results of risk and stakeholder analysis and communication plan, plan actions suggested by these including communication with external partners]] ||4½ md || [[TaskG.2]] [[TaskG.3]] ||KFC(2), TSH(1½) || Not started ||
||2 || [[ActionReleasetest5|Prepare releasetest. Goal: Running the migrated ingest code on test objects in test setup. Use Fedora tools to see they are ingested properly]] || 5 md. || Release test ||KFC(3½), TE(1½) || Not started ||

Agendas 2007-11-12

0. Agenda walkthrough

1. Iteration 5 status

For each action:

  • Action status (not started, in progress, done), time spent
  • Do estimates seem to hold
  • Does deadline seem to hold
  • Any information that should be shared
  • Any planning we need to do

Priority

Action Description

Estimated time

Tasks adressed

Responsible

Status

1

Design ingest module, migrate pre-analysis project ingest code

12 md

TaskA.4.1

TE (6 md), TSH (6 md)

Not started

1

Salvage data model from pre-analysis project, document, identify unresolved issues

6 1/4 md

TaskA.2.2, TaskA.2.3

BAM (2 1/4), MKE (4)

In progress

3

Identify "Gentofte" objects, design datamode

5½ md

TaskA.2.2 Collection

BAM (2), MKE(3½)

In progress

1

Study group with Asger and Jeppe: setup Idea/SVN, go through WBS, go through guidelines, identify relevant study material

10½ md

TaskF TaskG

TSH (½), KFC(1), JRG(4½), ABR(4½)

Not started

5

Present results of risk and stakeholder analysis and communication plan, plan actions suggested by these including communication with external partners

4½ md

TaskG.2 TaskG.3

KFC(2), TSH(1½)

Not started

2

Prepare releasetest. Goal: Running the migrated ingest code on test objects in test setup. Use Fedora tools to see they are ingested properly

5 md.

Release test

KFC(3½), TE(1½)

Not started

3. AOB

  • KFC Meeting with Media Department today 10.45
  • Use of project room