   ⇤ ← Revision 1 as of 2008-06-26 12:26:05   
  Size: 2118 
  
  Comment: Created by the PackagePages action. 
 | 
    ← Revision 2 as of 2010-03-17 13:12:47  ⇥ 
  Size: 2124 
  
  Comment: converted to 1.6 markup 
 | 
| Deletions are marked like this. | Additions are marked like this. | 
| Line 15: | Line 15: | 
| ||1 || [:ActionDesignAndSalvageIngestModule:Design ingest module, migrate pre-analysis project ingest code] || 12 md || ["TaskA.4.1"] ||TE (6 md), TSH (6 md) || Not started || ||1 || [:ActionSalvageDataModel:Salvage data model from pre-analysis project, document, identify unresolved issues] || 6 1/4 md || ["TaskA.2.2"], ["TaskA.2.3"] ||BAM (2 1/4), MKE (4) ||In progress || ||3 || [:ActionGentofte:Identify "Gentofte" objects, design datamode] || 5½ md || ["TaskA.2.2"] Collection ||BAM (2), MKE(3½) || In progress|| ||1 || [:ActionStudyGroup:Study group with Asger and Jeppe: setup Idea/SVN, go through WBS, go through guidelines, identify relevant study material] || 10½ md || ["TaskF"] ["TaskG"] || TSH (½), KFC(1), JRG(4½), ABR(4½) || Not started || ||5 || [:ActionRiskAndStakeholderResults:Present results of risk and stakeholder analysis and communication plan, plan actions suggested by these including communication with external partners] ||4½ md || ["TaskG.2"] ["TaskG.3"] ||KFC(2), TSH(1½) || Not started || ||2 || [:ActionReleasetest5:Prepare releasetest. Goal: Running the migrated ingest code on test objects in test setup. Use Fedora tools to see they are ingested properly] || 5 md. || Release test ||KFC(3½), TE(1½) || Not started ||  | 
||1 || [[ActionDesignAndSalvageIngestModule|Design ingest module, migrate pre-analysis project ingest code]] || 12 md || [[TaskA.4.1]] ||TE (6 md), TSH (6 md) || Not started || ||1 || [[ActionSalvageDataModel|Salvage data model from pre-analysis project, document, identify unresolved issues]] || 6 1/4 md || [[TaskA.2.2]], [[TaskA.2.3]] ||BAM (2 1/4), MKE (4) ||In progress || ||3 || [[ActionGentofte|Identify "Gentofte" objects, design datamode]] || 5½ md || [[TaskA.2.2]] Collection ||BAM (2), MKE(3½) || In progress|| ||1 || [[ActionStudyGroup|Study group with Asger and Jeppe: setup Idea/SVN, go through WBS, go through guidelines, identify relevant study material]] || 10½ md || [[TaskF]] [[TaskG]] || TSH (½), KFC(1), JRG(4½), ABR(4½) || Not started || ||5 || [[ActionRiskAndStakeholderResults|Present results of risk and stakeholder analysis and communication plan, plan actions suggested by these including communication with external partners]] ||4½ md || [[TaskG.2]] [[TaskG.3]] ||KFC(2), TSH(1½) || Not started || ||2 || [[ActionReleasetest5|Prepare releasetest. Goal: Running the migrated ingest code on test objects in test setup. Use Fedora tools to see they are ingested properly]] || 5 md. || Release test ||KFC(3½), TE(1½) || Not started ||  | 
Agendas 2007-11-12
0. Agenda walkthrough
1. Iteration 5 status
For each action:
- Action status (not started, in progress, done), time spent
 - Do estimates seem to hold
 - Does deadline seem to hold
 - Any information that should be shared
 - Any planning we need to do
 
Priority  | 
  Action Description  | 
  Estimated time  | 
  Tasks adressed  | 
  Responsible  | 
  Status  | 
1  | 
  Design ingest module, migrate pre-analysis project ingest code  | 
  12 md  | 
  TE (6 md), TSH (6 md)  | 
  Not started  | 
|
1  | 
  Salvage data model from pre-analysis project, document, identify unresolved issues  | 
  6 1/4 md  | 
  BAM (2 1/4), MKE (4)  | 
  In progress  | 
|
3  | 
  5½ md  | 
  TaskA.2.2 Collection  | 
  BAM (2), MKE(3½)  | 
  In progress  | 
|
1  | 
  10½ md  | 
  TSH (½), KFC(1), JRG(4½), ABR(4½)  | 
  Not started  | 
||
5  | 
  4½ md  | 
  KFC(2), TSH(1½)  | 
  Not started  | 
||
2  | 
  5 md.  | 
  Release test  | 
  KFC(3½), TE(1½)  | 
  Not started  | 
3. AOB
- KFC Meeting with Media Department today 10.45
 - Use of project room