Agendas 2007-11-22
0. Agenda walkthrough
1. Iteration 5 status
For each action:
- Action status (done/outstansing issues), time spent
- Any information that should be shared
- Any planning we need to do
Priority |
Action Description |
Estimated time |
Tasks adressed |
Responsible |
Status |
1 |
Design ingest module, migrate pre-analysis project ingest code |
12 md |
TE (6 md), TSH (6 md) |
In Progress |
|
1 |
Salvage data model from pre-analysis project, document, identify unresolved issues |
6 1/4 md |
BAM (2 1/4), MKE (4) |
Done with outstanding issues |
|
3 |
5½ md |
TaskA.2.2 Collection |
BAM (2), MKE(3½) |
Done |
|
1 |
10½ md |
TSH (½), KFC(1), JRG(4½), ABR(4½) |
In Progress |
||
5 |
4½ md |
KFC(2), TSH(1½) |
Not started |
||
2 |
3 md. |
Release test |
KFC(2½), TE(½) |
Not started |
3. Release test
4. Risks and stakeholders
- Go through tables
- Look at actions we need to take
5. End of iteration tasks
- Communication
- Steering committee
- Followup on task status
6. Next iteration
- Only JRG/ABR/KFC
- Suggest datamodel and pre-ingest
7. Next full iteration
- Starts 2007-12-17
- Suggest Summa integration, bit storage
8. AOB
- KFC has visited department