Starting DOMS framework on test collection
- Begun
- 2007-10-30
- Finished
- 2007-11-22
- Status
- Finished
- Due
- 2007-11-22
- Title
- Starting DOMS framework on test collection
This iteration starts the DOMS ingest framework and identifies a test collection.
At the end of the iteration we should be able to ingest a test collection in Fedora.
Iteration Actions
The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the Work Breakdown Structure (WBS).
Each action is associated with a priority, estimated time, tasks addressed, responsible developers and a status. The priority indicates the importance of the completion of the action, where the highest priority is indicated with 1, and the status indicates the current state of the action. The state may be one of the following: "Not Started", "In Progress" and "Completed".
Priority |
Action Description |
Estimated time |
Tasks adressed |
Responsible |
Status |
1 |
Design ingest module, migrate pre-analysis project ingest code |
12 md |
TE (6 md), TSH (6 md) |
Done with outstanding issues |
|
1 |
Salvage data model from pre-analysis project, document, identify unresolved issues |
6 1/4 md |
BAM (2 1/4), MKE (4) |
Done with outstanding issues |
|
3 |
5½ md |
TaskA.2.2 Collection |
BAM (2), MKE(3½) |
Done |
|
1 |
10½ md |
TSH (½), KFC(1), JRG(4½), ABR(4½) |
Done |
||
5 |
4½ md |
KFC(2), TSH(1½) |
In Progress |
||
2 |
3 md. |
Release test |
KFC(2½), TE(½) |
In Progress |