Iteration 23 Finalise datamodel, more bitstorage, start characterisation. Surveillance and documentation.

Begun
2009-10-27
Finished
2009-12-23 (Killed)
Due
2009-11-09
Status
In progress
Title
Finalise datamodel, more bitstorage, start characterisation. Surveillance and documentation.

Iteration Actions

The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the Work Breakdown Structure (WBS).

Each action is associated with a priority, estimated time, tasks addressed, responsible developers and a status. The priority indicates the importance of the completion of the action, where the highest priority is indicated with 1, and the status indicates the current state of the action. The state may be one of the following: "Not Started", "In Progress" and "Finished".

When an iteration ends please walk through the actions and follow these steps on the "iteration end meeting":

Priority Time used Time estimated Assigned Status Tasks adressed Notes
Actions/Datamodel 8 11md EAB, MAR, EK In progress [[Tasks/1/1/1]], [[Tasks/1/1/2]], [[Tasks/1/2]], [[Tasks/1/3]], [[Tasks/1/4]], [[Tasks/1/5]], [[Tasks/7/2]],
Actions/High level bit storage 1 10 md (ABR) 5md ABR In progress [[Tasks/4/3]] [[Tasks/4/4]]
Actions/Review characterisation interface 3 5md ABR: 2 PKO: 3 In progress [[Tasks/6/1]]
Actions/Surveillance 5 15md (KFC, includes testbed) 9½md JRG: 7½ KFC: 2 In progress [[Tasks/2/1/5]] [[Tasks/2/2/2]] [[Tasks/7/5]]
Actions/XACML stuff 9 5md PKO: 2 JRG: 2 EK: 1 Not described [[Tasks/3/4]]