Iteration 8: Reaching Milestone 2

Begun
Finished
Due
Status
Finished
Title
Reaching Milestone 2

This iteration should bring us to Milestone 2 Early Ingest and Trivial Search - Temporary Production System. We need to follow up on a few actions from iteration 7, which left us with a basic working system, and we need some documentation and we are going to set up the actual production system.

Iteration Actions

The below table contains all the planned actions for this iteration. Each of the actions may contribute to the completion of one or more tasks from the Work Breakdown Structure (WBS).

Each action is associated with a priority, estimated time, tasks addressed, responsible developers and a status. The priority indicates the importance of the completion of the action, where the highest priority is indicated with 1, and the status indicates the current state of the action. The state may be one of the following: "Not Started", "In Progress" and "Completed".

Priority

Action Description

Estimated time

Tasks adressed

Responsible

Status

5

Bit Storage Test

2 md

TaskA.3

Not Started

1

Agree on system setup (ingest+final bitstorage+tomcat)

5 md

TaskA.3

ABR+JRG

Done

2

Deliver start/stop scripts, documentation

7-9 md

TaskA.2, TaskD.3.2

JRG+TSH

In progress

*

XSLT's Unique Subjects

1-2 md

TaskB.1

*

Done

2

XSLT's to Dorete and/or Gitte

1 md

TaskB.1

JRG+GB

In progress

4

All Summa Tasks (harvest, ingest, index)

1 md

TaskB

TE+Summa

Not Started

1

Release Test

5-7 md

Not Started

9

Opensource

KFC

In progress

7

Year Book Collection (img.s, empty files, PID prefix)

3 md

TaskA.4.2

BAM

In progress

2

Minor Tasks (prop.s, TODOs, manufacturer)

4-9 md

TaskA.4.1,TaskA.4.2,TaskB.2

ABR+TSH

In progress